The strength of our relationship with the producer started several years earlier and built on supporting the company with operational and engineering support. The areas covered included West and South Texas, Eastern New Mexico, and Louisiana. With the success of the company’s drilling program in the Permian Basin, our duties grew to include a 35 MMscfd cryo plant. We acted as owner’s engineers evaluating pipeline capacity, field vs plant compression, field dehydration, process simulations, PHA (Process Hazard Analysis), site selection, cryo plant supplier selection, and project management. We also designed and manufactured a direct fired 550 bbl/day condensate stabilizer providing 9 RVP product. Under Newpoint’s supervision, we completed the project in Loving County, Texas on time and on budget.
World’s Largest Catalytic Oxygen Removal Plant
According to our client, the world’s largest catalytic oxygen system was installed in California using our proprietary technology. This plant can treat up to 140 MMscfd of gas at 1140 psig from 225 ppmv oxygen to less than 5 ppmv.
350 GPM Amine Plant
A new 350 gpm amine plant and hot oil system was delivered to NW Oklahoma. The planted is treating 120 MMscfd from 1.15 mol% carbon dioxide to the less than 50 ppmv. Utilizing modular design, the interconnecting piping was installed in 1.5 days with a two person crew.